• Hours of Operations 9:00AM-5:00PM
  • After Hours Water Emergencies 910-367-1537
  • After Hours Sewer Emergencies 910-367-2084
  • View/Pay Bill
  • Search 
Credit/Debit Card Payments Down -

Credit/debit card payments made online are not working at this time. We do not have a timeline on how long it will be unavailable. The system will allow the customer to go through the process but it rejects the payment later. Customers can make payments using their checking account, just not credit/debit cards. 

Click here to learn more    |    Aquifer-Sourced Reverse Osmosis Water Treatment Plant - Clean, contaminant free water at no water rate increase coming early 2022! Click here to learn more    |    Special Election -

A special election on the question of Brunswick Forest's annexation into H2GO's district will be held concurrent with the November general election.

Click here to learn more    |    Smoke Testing -

Smoke testing will occur throughout Magnolia Greens over the next several weeks.

Click here to learn more    |    After-Hours Emergencies - For water emergencies, call 910-367-1537. For sewer emergencies, call 910-367-2084. Click here to learn more    |   

US 17 Interceptor Sewer & Regional Pump Station

Project Description: The first phase to extend and upgrade sewer services to the south US 17 corridor. In addition to relieving existing daisy-chained lift stations along Lanvale Rd, and providing available service to the US 17 corridor northeast of the Military Ocean Terminal Sunny Point Railroad (MOTSU RR), the current US 17 interceptor project was designed and sized to regionally serve undeveloped areas southwest of the MOTSU RR including areas near the US 17 & Hewett Burton/Goodman Rd intersection

Current Project Budget: $3 million
Funding Source(s): Capital Improvement Budget
Project Schedule: October 2017 - January 2019