Active Capital Projects

Brunswick Regional Water and Sewer currently has several capital project in various stages of completion in addition to the proposed  Reverse Osmosis Watertreatment Plant.

 
Water Transmission Main Upgrade
 
Project DescriptionInstallation of an 18” water transmission line to maintain adequate pressure during peak demand times. 
 
Current Project Budget: $1.6M
 
Funding Source(s):  Water capital reserves
 
Project Schedule:
  • Bidding – October 2015
  • Const. – 6 mos.
  • Complete – May 2016
 

 
Azalea Plaza Estates MHP Water Distribution System
 
Project DescriptionInstallation of a 6” water line to serve 54 current homes and more than 74 individual lots.  Community Betterment. Currently, the MHP is served by an aging 2” water line that is inadequate and prone to leaks.
 
Current Project Budget: $265,000
 
Funding Source(s):  Special Assessment
 
Project Schedule:
  • Construction – Sept. 2015
 

 
Compass Pointe Force Main
 
Project DescriptionInstallation of 7,600 feet of 10 inch sewer line to serve the Compass Pointe subdivision through full build out that may include more than 2,500 homes and a commercial center. 
 
Current Project Budget: $660,000
 
Funding Source(s):  Developer paid impact fees.
 
Project Schedule:
  • Bidding – October 2015
  • Const. – 6 mos.
  • Complete – May 2016
 

 
Ploof Road Sewer Extension
 
Project DescriptionInstallation of a low pressure sewer line in an unserved area along Ploof Road. 
 
Current Project Budget: $100,000
 
Funding Source(s):  Water capital reserves.
 
Project Schedule:
  • Design –  August 2015
  • Permitting – Sept. 2015
  • Bidding – Nov. 2015
  • Const. – Jan. 2016
  • Complete – March 2016

 
Regional Lift Station/Interceptor – Engineering Services
 
Project DescriptionDesign for construction of a regional lift station – interceptor sewer system along U.S.  17 Highway to alleviate bottlenecks in southwest end of district.  Also, this project would provide additional sewer availability along U.S. 17 Highway South towards Lanvale Road.
 
Current Project Budget: $3.4M
 
Funding Source(s):  Waterwater capital reserves.
 
Project Schedule:
  • Design – Sept. 2015
  • Permitting – Dec. 2015
  • Bidding – Feb. 2016
  • Const. – Mar. 2016